September 26
-
01. Milestone of the Month
- Construction momentum continued, with the Danoa Camp completed, major plant equipment advancing into fabrication, additional construction contracts awarded, and zero lost-time or medical treatment injuries.
-
02. Construction Progress
- Bulk earthworks completed for the construction camp, operations village and wet-plant area.
- Two additional production boreholes completed with headworks, bringing the total to three on-site production boreholes.
- Process plant earthworks continued, with completion targeted for October.
- Substation and laydown-area earthworks progressed, paving the way for electrical and concrete contractor mobilisation.
-
03. Major Equipment and Procurement
- Transport & Logistics, Steelwork and Platework contracts awarded.
- Bolted CIL tanks, SAG/Ball mills and thickeners advanced into fabrication.
- Key mechanical packages awarded, including vibrating screens, electrowinning cells and water-treatment plants.
- EPCM/Supply progress running ahead of schedule.
- Internal local procurement committee established, with 145 local suppliers registered in the local vendor database.
-
04. Workforce & Recruitment
- Workforce climbed to 622 people, with 163,282 hours recorded.
- Earthworks contractor reached 171 on-site personnel.
- Seven new starters in September, strengthening HR, emergency response and technical capability.
- Project internship programme approved for launch.
-
05. Safety
- 500,000 LTI-free hours milestone achieved.
- Contractor safety audit scores remained strong.
- Corrective-action closure rate reached 84.7% across 1,082 recorded actions, supporting continuous improvement.
-
06. Community & Environment
- Joint site visit with National Maritime Affairs and CIAPOL to review environmental and maritime compliance.
-
07. Next 30 Days
- Complete Operations Village earthworks and camp handover.
- Mobilise the concrete contractor, continue water bore drilling and award major equipment packages.
- Complete substation bulk earthworks to enable electrical contractor site establishment.
- First concrete pour for the process plant.
August 26
-
01. Milestone of the Month
- Significant progress on accommodation facilities, site infrastructure and major equipment procurement for processing plant and +60 km grid line extension.
- Site prepared for first concrete pour in the next weeks.
-
02. Construction Progress
- Danoa camp expansion first accommodation units completed and undergoing commissioning with relocation of teams closer to site.
- Water supply development – 26 boreholes drilled, additional production bore infrastructure installed.
- Earthworks progressed across construction camp, operations village and process plant areas, including cut-to-fill activities, compaction works and site preparation.
- +20 km local access road refurbished in anticipation of rainy season.
- Rehabilitation of Bouna airstrip to begin charter flights to site.
-
03. Safety
- No lost-time injuries or medical treatment injuries during July.
- Safety focused on training, inspections, emergency preparedness and continuous improvement.
- Contractor safety audit scored 89%, reflecting ongoing engagement with health and safety performance.
-
04. Major Equipment and Procurement
- Key equipment progressed: cyclone clusters, primary jaw crusher, bolted CIL tanks, high-rate thickeners, slurry agitators and oxygen plant.
- Contracting advanced across logistics, structural steel, platework fabrication and tank installation packages.
- First orders of long-lead items for power grid line extension.
- Construction camp and HDPE liner materials deliveries continued.
-
05. Workforce & Recruitment
- Over 550 people working on site.
- Project contractors recruited 17 local labourers in July alone, thanks to ongoing local employment initiatives.
- Preparation of literacy, apprenticeship and internship programmes for construction phase and operation preparedness.
-
06. Community & Environment
- In July, 42 stakeholder engagement meetings covered employment, procurement, community development and compensation.
- No environmental incidents recorded.
- Crop inventory and evaluation completed on 300 ha out of additional 1600 ha of second phase land compensation for main project development area.
-
07. Next 30 Days
- Finalise water bore drilling and equip 4–6 bores.
- Receive approximately 1million2 HDPE liner for TSF and Process water ponds.
- Complete 48 Room expansion of Danoa Camp and receive 176 rooms for the construction camp.
- Launch of power grid line works.
- Arrival of first equipment at Abidjan port.
- First concrete pour.
July 26
-
01. Milestone of the Month
- EPCM construction management team on site.
- Concrete works awarded – civil works underway.
-
02. Construction Progress
- Earthworks contractor mobilisation – approx. 40 heavy vehicles now on site.
- Over 20km of access roads established and 74 hectares cleared for construction camp, mine village and process plant areas.
- Temporary Starlink-powered comms infrastructure established – internet, Wi-Fi, VHF tower, and radios, while 4G tower comes online.
-
03. Safety
- Zero lost-time injuries.
- Zero medical treatment injuries since construction commenced.
- Emergency management plan finalised.
-
04. Procurement Activity
- Jaw crusher, thickeners, structural steel and platework awarded.
- HV power line and substation contracts awarded.
- Concrete works, HDPE liner and permanent accommodation camp contracts awarded.
-
05. Workforce & Recruitment
- Over 120 employment opportunities advertised.
- 22 local community members employed during June.
- Recruitment continued to prioritise host community employment.
June 26
-
01. Milestone of the Month:
Ground broken on the Process Plant, with early works and bulk earthworks advancing across key site infrastructure, including access roads and water boreholes.
-
02. Construction Progress:
- Danoa Camp: Kitchen and dry mess upgrades handed over; 48 additional rooms in delivery.
- Bulk earthworks underway at Process Plant and Permanent Village.
- Site connectivity infrastructure commissioned.
- CIS now managing camp catering and infrastructure.
-
03. Safety:
- 92 days without a Lost-Time Injury (LTI) since construction commenced.
-
04. Long Lead Items Ordered:
- SAG and Ball Mills: in manufacture. Bolted CIL tanks ordered. HDPE liner for tailings storage facility secured.
- Construction camp and associated facilities awarded.
- HV long lead tenders adjudicated and recommended for award.
-
05. Work Packages in Procurement:
- Permanent (operations) village package awarded.
- EP & Supply, Construction Management Services, transport & logistics progressing through tender and contract negotiation.
-
06. Workforce:
- 332 people currently on site.
- 87% Ivorian nationals; 24% recruited from host communities.
- 89% men / 11% women.
-
07. Recruitment:
- 14 community members hired locally.
- 2 senior project personnel onboarded.
- 7 further project roles confirmed.
-
08. Community & Environment
- Full support secured from community leaders and parliamentary representatives for access to early works areas.
-
09. Next 30 Days:
- Grid power contract awards expected.
- Early works and bulk earthworks to continue progressing.