In December 2025, Resolute updated the Definitive Feasibility Study (DFS) which outlines a robust, high-margin project with average annual gold production of 169,000 ounces (oz) at an all-in Sustaining Cost (AISC) of US$1,406/oz over a 13-year mine life. Resolute is waiting to receive the Exploitation License and upon receipt expects to advance the project towards construction in H1 2026.
Doropo is located in north eastern Côte d’Ivoire approximately 480km north of Abidjan. The project has received regulatory approval for its Environmental and Social Impact Assessment and the environmental permit was awarded in June 2024.
The updated DFS envisages a multiple open pit operation mining shallow dipping gold structures. The carbon-in-leach processing plant outlined in the updated DFS has a 4.9 Mtpa of installed capacity for fresh ore and comprises a crushing circuit, a SAG Mill and gold extraction circuit.
For further Information:
2024 Doropo NI43-101 Technical Report